What is residual risk?
Residual risk is the part of a risk that an organisation knowingly carries after its risk treatment. Under BSI Standard 200-3, chapter 6.1, risk classification and treatment are repeated until the organisation's acceptance criteria are met; the remaining risk is then put to management for approval. In ISO/IEC 27001, the risk owners approve the treatment plan and accept the remaining risks under clause 6.1.3.
A planned control describes an expected improvement; the risk falls only once the control is implemented and works.
Three states: inherent, current, residual
| State | Controls taken into account | What it is used for |
|---|---|---|
| Inherent risk (gross risk) | none | shows what the existing controls achieve |
| Current risk (net risk) | those effective today | steering and reporting |
| Residual risk | additionally the agreed, still planned ones | approval and whether the effort pays off |
If you calculate residual risk as "inherent risk minus the effect of controls" and count only the controls effective today, you get current risk. Once all agreed controls are implemented, the two figures coincide. Define in your risk policy which state is called "residual risk" and use it the same way in every report. More on the distinction in inherent risk.
Worked example: two controls, two effects
Fictional example: accidentally deleted customer data interrupts a service and causes recovery costs. Assume at most one such event in the coming year. The figures in this example are invented for illustration.
| State | Annual likelihood | Loss per event | Expected annual loss |
|---|---|---|---|
| inherent, without the two controls | 20% | €100,000 | €20,000 |
| current: a restorable backup lowers the loss | 20% | €30,000 | €6,000 |
| residual: tighter deletion rights also lower the likelihood | 10% | €30,000 | €3,000 |
Expected annual loss = annual likelihood × loss per event.
The backup changes the loss, not the event. The tighter rights in access control change the likelihood. A single percentage for the "effectiveness" of both controls would hide that difference.
Does the planned control pay off?
The planned control lowers the expected annual loss from €6,000 to €3,000, a reduction of €3,000. If running it costs €2,000 a year, a benefit of €1,000 remains.
If it only lowers the likelihood to 15% instead of 10%, the expected loss is €4,500. The reduction of €1,500 is then €500 below the cost. The break-even point is about 13.3%: (€6,000 − €2,000) ÷ €30,000. Decision-makers therefore judge whether the tighter deletion rights reliably push the likelihood below 13.3%.
Justify every assumption: incident history and the volume of the affected activity for likelihood, downtime and recovery effort for the loss, tested for example in a recovery exercise. Where data is thin, calculate a range. Expected loss is an average, not a ceiling for a single incident.
How is residual risk accepted?
Residual risk is accepted when the responsible body has approved it and the decision is documented. That takes four items:
- a named risk owner with authority for the affected area;
- a threshold rule stating from which risk level senior management decides, derived from the risk acceptance criteria, which under BSI Standard 200-3 (chapter 2) depend largely on the risk appetite;
- a justification with the assumptions that applied at the time;
- a date or trigger for review.
BSI Standard 200-3 gives three example reasons for accepting higher risks as well:
- The threat only causes harm under very specific conditions.
- No effective countermeasures against the threat are known, and it can hardly be avoided.
- The effort and cost of effective countermeasures exceed the value to be protected.
Management at particularly important entities (besonders wichtige Einrichtungen; "essential entities" in the NIS2 Directive) and important entities must implement the risk management measures under § 30 of the BSI Act (BSIG). It must also oversee their implementation (§ 38(1) BSIG). § 28(5) and (6) BSIG exempt, among others, financial entities under DORA. Where § 38 applies, the threshold rule should therefore set out how management learns of accepted residual risks in this area.
The documented approval helps a German management board show that it decided on the basis of adequate information (§ 93(1) sentence 2 AktG). For managing directors of a GmbH, § 43(1) GmbHG requires the care of a prudent businessperson.
Reassess when an assumption changes: the threat situation, the legal situation, a compensating control that falls away, an incident in a comparable area, or the system itself. Once a control is completed, check that it works before the planned reduction counts as achieved.
Residual risk in Rizzqo
In Rizzqo, you assess each risk in euros, from its likelihood and impact. Each measure runs as a task with the reduction you expect from it. A planned task lowers the expected risk, and only a completed task lowers today's risk, so you see how much of the reduction is still outstanding.

